The acceleration instruction that was never documented
The situation
The client's project manager visits site and tells the site manager to accelerate the concrete frame works by two weeks to allow an early handover of Level 3 for fit-out to begin. The site manager passes the instruction to the foreman. Additional resources are mobilised. Overtime is worked. The frame is accelerated.
The dispute
At final account, the contractor submits a claim for £84,000 in acceleration costs. The client's team has no record of the instruction. The project manager who gave it has moved to another role. The client denies the instruction was ever given and refuses to certify the costs. Without a CVI (Confirmation of Verbal Instruction), the contractor has no contemporaneous record of the instruction, no written confirmation, and no signed agreement to the cost. The £84,000 is written off.
The prevention
A CVI raised on the day of the instruction — or even the following morning — would have confirmed the instruction in writing, identified the accelerated scope, and requested the client's confirmation of the cost basis. An instruction that is confirmed in writing within 24 hours is extremely difficult to deny six months later at final account.